Consultation
Quote
Contract
Design
Permits
Site Preparation
Pre Site Inspection
Excavation
Structural Steel
Rough Electrical & Plumbing
Pre Gunite Inspection
Gunite
Tile / Stone / Coping
Decking
Equipment Set
Pool Clean-Out
Fence Replacement / Alarms
Pre Plaster Inspection
Plaster
Pool Fill Up
Site Clean-Up
Equipment Start-Up
Customer Orientation
Final Inspection
1st Month's Maintenance

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
10. Rough Electrical & Plumbing
Main drain lines are dug and placed prior to structural steel. 

Following the steel placement the remaining electrical and plumbing is installed in the pool and back to the equipment area. 

All plumbing is placed under pressure to ensure integrity through out the project. 

The pressure on the piping in not removed until after concrete in installed guaranteeing a flawless system.